Anti-skid surface to be installed on A18

Anti-skid surface to be installed on A18

Final touches to the A18 road safety improvement scheme will be taking place between Tuesday 10 May and Thursday 19 May, with delays possible subject to weather conditions.

The final element of works includes installation of new anti-skid surface and carriageway lining and will be carried out in three phases

This will also incorporate safety works for other areas which is outlined on the NELC website.

As outlined on NELC website, the phases have a breakdown:

Phase one – Waltham Road / A18 junction.

“In phase one, anti-skid surfacing and lining will be carried out between Tuesday 10 May and Friday 13 May, between 6pm and 6am. To ensure a safe working environment, Waltham Road will be closed during this time, preventing access to the A18 from Barnoldby le Beck. Access to the north and south of the A18 at this junction will be under a convoy system.”

Phase two – Barnoldby le Beck

“Phase two will include anti-skid surfacing and carriageway lining along Waltham Road which will be taking place between Thursday 12 May and Thursday 19 May, from 10am to 3pm, under Stop and Go signs.”

Phase three – A18 between the A16 Ludborough bypass and the A18 Livesey Road junction

“Phase three works in Lincolnshire County Council’s boundary will be taking place between Tuesday 17 May and Thursday 19 May, from 10am to 3pm, under Stop and Go signs. Anti-skid surfacing and additional lining will be required on the A16 at this junction, which will require traffic signals due to the volume of traffic.”

 